Asynchronous Parallel Electromagnetic Transient Simulation of Large Scale Power System

Gesong Chen, China Electric Power Research Institute
Xiaoxin Zhou, China Electric Power Research Institute

Abstract

An asynchronous parallel electromagnetic simulation method for large scale power system is developed, in which the original system is divided into two subsystems, A and B. Subsystem A is the local system including the disturbance source and any devices that should be simulated in details. Subsystem B is the external system consisting of all the other part of the system. The time domain digital simulation of subsystem A and B are executed by two independent processes with different time-steps. Signal transmission between A and B is implemented at each time step by a series of time varying Norton equivalent circuits and equivalent voltage sources. Because the digital simulation for subsystem A and B are processed in parallel, and simulation time of process B lags that of process A, so it’s called asynchronous parallel electromagnetic simulation method. The basic principle, implementation procedure and error analysis of this new method are discussed, computer coding is also implemented in one version of EMTP program. Practical power system simulation and other application with the new method are also presented.

Submitted: January 12, 2005 · Accepted: January 31, 2005 · Published: February 24, 2005

Recommended Citation

Chen, Gesong and Zhou, Xiaoxin (2005) "Asynchronous Parallel Electromagnetic Transient Simulation of Large Scale Power System," International Journal of Emerging Electric Power Systems: Vol. 2 : Iss. 1, Article 1.
Available at: http://www.bepress.com/ijeeps/vol2/iss1/art1

 
 
 
 

ISSN: 1553-779X ©1999-2008 The Berkeley Electronic Press™ All rights reserved.

To submit, subscribe, recommend this journal to your library, or sign up for email alerts, please visit: http://www.bepress.com/ijeeps